|
[ Home | History | Overview | Environment | Contact Us | Community | Clean Coal | Customers ] | |||||||||
| COAL MINING UNCOVERED | ||||||||||
|
Mining coal is easy. Getting to it is the hard part.
The bucket on the dragline weighs 32 tons and can hold 33 cubic yards of material. New Caterpillar 785 trucks can haul 150 tons of material. In April 1996, the water truck and other heavy equipment was mobilized to help fight and contain the fire that partially burned the Princess Hotel at nearby Denali National Park. Light blasting is done in order to loosen the overburden and coal before it is handled. |
Uncovering Coal is the Biggest JobMining coal is easy. Getting to it is the hard part. At Usibelli Coal Mine, up to 200 feet of unconsolidated sandstone or "dirt" must be moved to uncover the top seam of coal. Another 80 feet must be moved to uncover the second seam. Dragline does the "dirt" workThe most efficient machines for moving large volumes of dirt are draglines. In 1977, UCM made a major investment by purchasing a 1300W Bucyrus-Erie Walking Dragline. The dragline arrived in parts on 26 railcars and 40 trucks during December 1977. It took 11 months to assemble the 2100 ton machine. Named "Ace-in-the-Hole" by Healy school children, the dragline is the largest land-based machine in Alaska. The acquisition of "Ace-in-the-Hole" made it possible to double production and initiate UCM's Korean export contract in 1985.
With its Due to the weight of the machine, moving it on tires or tracks is not possible. The dragline moves by "walking." Shoes on either side of the machine lift its base partially off the ground and drag it backward. Each step takes about 40 seconds and moves the dragline approximately 7 feet. While it takes only one person to run the machine, there are two dragline operators on duty at all times. One operates the dragline from the cab while the other does routine maintenance. For safety reasons, the operators switch positions every hour. The dragline is powered solely by electricity. A Load Stabilizer System consisting of a 42 ton flywheel and motor/generator serves as a buffer between the dragline and the local electrical grid. The flywheel stores energy to be used whenever the dragline's electrical demand increases too quickly for the local grid. This enables the dragline to operate without causing power fluctuations for other electrical customers. The dragline has several buckets, which are used on a rotating basis. Each bucket is used on the dragline for about 45 days. After that period, the bucket must be serviced and its ultra-high molecular weight plastic liner must be repaired or replaced. Shovels, backhoe strip overburden, load coal
While the dragline does the majority of the excavation work at the mine, smaller excavators are needed. Two track mounted O&K RH120C hydraulic shovels help to strip overburden in areas too difficult for the dragline to maneuver and to load trucks with rock and gravel for construction projects. An identical machine, but configured with a backhoe, loads coal trucks. Both the backhoe and the shovels have
The largest hydraulic shovel in Alaska was added to UCM's fleet in August 1997. The O&K RH-170 shovel has a 26 cubic yard bucket and can load the new Trucks, other equipment support operations
A fleet of 15 trucks is used to haul coal and rock. Two WABCO trucks with
In 1995, a Caterpillar 785 haul truck was added to the fleet. The new truck has a capacity of 150 tons, over 50% greater than the Many other pieces of equipment are needed to support day-to-day activities. UCM has several dozers including a Caterpillar D11N. The D11N is one of the largest tracked dozer manufactured in the world. Two road graders operate during day and night shifts to keep the haul roads smooth for the big trucks. A 75-ton, 14,000 gallon water truck provides road dust control. A high-pressure nozzle mounted on the tank truck is used to clean muddy equipment and fight fires. Blasting loosens materials, casts overburdenBoth overburden and coal are very difficult to excavate. Light blasting is done in order to loosen the overburden and coal before it is handled. A specially designed powder truck transports, mixes and loads explosives into each drill hole. In some areas of the pit, a technique called "cast blasting" is used to help strip overburden. In cast blasting, the drill holes and explosive charges are designed so that a portion of the overburden is cast laterally by the force of the explosion into the adjacent mined out pit. This technique, when it can be used, reduces the amount of overburden that the dragline handles by up to 50%. |
|
||||||||
| [ Home | History | Overview | Environment | Contact Us | Community | Clean Coal | Customers ] | ||||||||||